CCPM Consulting

Critical Chain Project Management

  • Home
    • Methods
  • Theory of Constraints
    • Project Management
    • Project Rescue
    • Manufacturing Management
    • Supply Chain Logistics
    • Strategic Analysis
  • Test Drive CCPM
  • Articles
    • Transition to CCPM
    • Projects Early and Under Budget
    • Operations
    • Project Management
    • How and Why
    • White Papers
  • Pink Pyramid
    • Pink Pyramid | The Story
    • Pink Pyramid | Focus Your Attention
    • Comments or Questions | Order Yours Today
    • Pink Pyramid | Feedback
  • Contact
  • Client List
    • Client List
    • Companies Using Theory of Constraints Methods
    • Favorite Sites

Critical Chain is Crazy Stuff!

January 12, 2015 by Skip Reedy Leave a Comment

If Project Management is truly important to you, this will light your fire!

It may seem like Crazy Stuff, but CCPM feels like Cruise Control for Projects. We will show you how to do things you don’t know are possible. We want you to know why you can, so you can take others there.

Project Management should not be difficult. It’s not.

Filed Under: Project Management Tagged With: CCPM, Critical Chain, PMI, project management

Critical Chain Project Management

September 26, 2012 by Skip Reedy Leave a Comment

Critical Chain Project Management (CCPM) focuses attention on the few tasks that determine the duration of the project. Projects can be completed 25 to 50% faster, and at less cost. The critical chain is the constraint of a single project. CCPM is most effective in complex environments and with multiple projects that share resources.

Critical Chain Project Management is based on the Theory of Constraints. Drum-Buffer-Rope (DBR) is primarily used to manage production and CCPM is primarily used to manage projects. The distinction between projects and production is blurred. Is building a $200 million aircraft considered production or a project? The only real distinction is how you want to pay attention to the work. DBR monitors the Drum and Buffer, not the process. DBR does not directly track each job or item. CCPM tracks the project as it flows through each resource, so it doesn’t get delayed. High value and importance projects use CCPM to continuously monitor status with confidence.

Critical Chain Project Management (CCPM) uses aggressive task durations with a buffered project commitment. Normal variation in task duration is absorbed by time buffers. Critical Chain focuses attention on the few tasks that impact the actual duration of a project, and it changes behaviors from only meeting due dates to completing tasks quickly. Critical Chain is most effective with complex, multi-project programs that share resources.

The Critical Chain is the longest, task or resource dependent, chain of tasks in a resource loaded and leveled project. Critical Path Method only considers task dependencies. The Critical Path can have parallel tasks requiring the same limited resources.

Critical Path Method

The Critical Path can change during execution. The Critical Chain does not change because it becomes a baseline to measure Critical Chain work completed.

CCPM estimated task durations are based on effort only. No allowances are made for interruptions or distractions of any kind. Each task is considered to have a 50% probability of completing on time. Safety, contingency and allowances for delays (stuff happening) are aggregated at the end of the project (and at the end of feeding chains) in buffers.

Buffers are sized at 50% of the length of the chains they protect. Buffers do not protect individual tasks. Buffers do not belong to management. Buffers can be used by any task and they exist to protect the project commitment. The Project Buffer belongs to the customer.

Critical Chain Project Management

Aggressive tasks are often estimated at 50% of the normal estimate. The Critical Chain is about half the length of the Critical Path. Add in a Project Buffer of 50% of the Critical Chain and the total committed project length is 75% of the Critical Path committed length. Critical Chain projects, even though shorter, average being on time 95+%. Many of them complete in half the Critical Path time.

During project execution, a number of rules and behaviors must be followed –

  • Tasks and projects must be prioritized.
  • Higher priority tasks have precedence for limited resources.
  • A resource is to work diligently on one task until completed.
  • Resources are to turn in work when completed (task deliverables are available).
  • Tasks must have all inputs available before starting.
  • Task status is to be reported as Remaining Duration (effort only).
  • Status is collected frequently, usually daily.

Project execution decisions are based on Buffer Management. If a task takes longer than its aggressive planned duration, the buffer will be absorbed. If a task completes in less time than planned, the buffer will recover (grow).

For every project, the percent of Buffer Used (%BU) is compared with the percent of Critical Chain Completed (% CCC). The relative buffer impact (% BU / % CCC) is used to prioritize management’s focus where it is most needed. Resource assignments and special assistance are based on this Buffer Management. During execution, these high priority tasks get management attention. Lower priority (less buffer impacting) tasks receive very little management attention.

Task start and due dates are relatively unimportant in CCPM. What is important is completing the most important work quickly, so the project is completed quickly.

Critical Chain is like having Cruise Control for your Projects

Filed Under: Project Management

(425) 923-5750

Recent Posts

  • Critical Chain is Crazy Stuff!
  • Why Collect Daily Status
  • Critical Chain Project Management or Drum Buffer Rope Production?
  • Why the Critical Chain must not change?
  • Estimates are Numbers

Critical Chain

Critical Chain Project Management (CCPM)
A method of managing any kind of project by focusing attention on the few tasks that determine the project duration.
Completing tasks (and the project) quickly can result in a 25 to 50% shorter project.
It provides exceptional current status so delays and problems can be resolved and mitigated early.

5 Secrets of Critical Chain

"Test Drive" 5 Secrets of Critical Chain Project Management
that will speed up your project effortlessly.

You will receive one each week
so you can experience their impacts and see how they build
on each other.

These Secrets of Critical Chain
will help get your project done early.

Sign up and receive the First One Now!

We respect your email privacy

Email Marketing by AWeber

Copyright © 2021 · Dynamik-Gen on Genesis Framework · WordPress · Log in